A New Jersey home-care agency

The audit · document 02 of 07

Process map — the weekly paperwork, traced

How a week of delivered care becomes reviewed, official, filed documentation today — every time measured, nothing estimated from memory.

How this was traced

Median across the four measured cycles: 24 h 15 m of office hands-on work; a week filed 8 days after it ends. The full grid is in the appendix.

Four complete cycles replayed from the submission log and SharePoint’s filing timestamps; off-system steps — paper notes, calls, the Sunday reconstruction — timed live during shadowing; the 16-day worst week reconstructed from December’s records.

Where the 24 h 15 m goes

One typical week, as one bar. Each block is a step’s share of the office’s working time — the red blocks are pure re-typing and rebuilding, and they are almost half the total.

pure re-typing & rebuilding — 10 h 45 m chasing & correction tag — 9 h 45 m review proper — 2 h 30 m intake & sorting — 1 h 15 m

The eight steps

Owner, hands-on time, what it waits on, and where it breaks — step by step. Steps 1–2 are the workforce’s; steps 3–8 are the office’s.

01

The visits happen

owner each DSPhands-on notes all weekwaits on Sunday

DSPs care for participants at home — time, activities, assistance given, mileage. Most keep paper notes in the car between visits, to be turned into forms later.

observed · notes on paper in the car; two workers photograph them nightly — most don’t

Where it breaks: the record is made twice — once in the car, once on Sunday — and the second time is partly from memory.

02

Sunday-night submission

owner each DSPhands-on ~45 m per workerwaits on nothing — it just slips

The week’s forms filled from the notes and submitted through the forms platform — or on paper for a few — by the Sunday 8 pm deadline.

log · median week: 52 of 70 packets in by the deadline · the other 18 arrive Monday–Wednesday, some only after a call

Where it breaks: the deadline has no reminder and no teeth — a missing packet is invisible until someone notices it missing.

03

Monday intake & sorting

owner office coordinatorhands-on 1 h 15 mwaits on what didn’t arrive

Platform submissions opened one by one, emailed PDFs saved, paper packets typed in, each logged in the tracker — and the who’s-missing list drafted.

observed · Monday 08:10–09:40 — exports opened one by one; the missing list drafted from memory and inbox scrolling

Where it breaks: the missing list is a memory exercise (K1) — two workers were chased for packets they had already sent.

04

The chase

owner office coordinatorhands-on 5 h 30 mwaits on callbacks — days

Calls and texts to the 18 workers whose packets are missing or incomplete, Monday through Wednesday, threaded between everything else the office does.

log · week 3: 21 chase calls and texts across three days · median first response: 11 h

Where it breaks: chasing is nobody’s job description — it eats the coordinator’s week in ten-minute bites.

05

Re-key & reconcile

owner office managerhands-on 7 hwaits on steps 03–04

Hours and mileage typed again into the pay sheet and the billing sheet, then checked against a third spreadsheet holding each participant’s authorized weekly hours.

observed · the same worker-week open in three windows side by side — form, pay sheet, billing sheet

Where it breaks: triple entry is where typos enter — and the authorized-hours check happens after the care was already delivered (K2).

06

The review

owner office coordinatorhands-on 2 h 30 mwaits on steps 03–05

Each packet read against the participant’s service plan and authorized hours: do the notes match the plan’s outcomes, do the times add up, is everything signed.

observed · packets checked against the plan binder — whose newest plan was five weeks old (K5)

Where it breaks: errors found here are already a week old — and some outcomes being checked are no longer in the plan.

07

Correction round-trips

owner coordinator + the workerhands-on 4 h 15 mwaits on phone tag — days

Fifteen packets a week go back to their workers — a missing signature, a thin outcome note, overlapping times — by phone and text. Corrected versions re-enter at step 03.

log · median week: 15 packets returned · round-trip median 2 days, worst 6

Where it breaks: a returned packet repeats the whole loop — intake, re-key, review — a second time.

08

The official form & filing

owner office coordinatorhands-on 3 h 45 mwaits on everything above

The state-format multi-page form rebuilt by hand from the pieces — data pasted in, signature pages attached, a PDF made per worker-week — then saved into SharePoint folders one by one and the tracker updated.

files · SharePoint timestamps: filing lands in one batch the following Monday–Tuesday · two packets found mis-filed under the wrong participant during fieldwork

Where it breaks: three template versions circulate (K3), and hand-filing mis-files quietly — found only when someone goes looking.

Anatomy of the worst week — 16 days

December’s holiday week, reconstructed from the log and the filing timestamps. Not one big failure — small waits and one absence, stacked.

  • Day 0The week ends into a holiday weekend. 29 packets missing at the deadline. Nothing moves for two days.
  • Day 3The coordinator returns to a double pile — then goes home sick. The pile waits again.
  • Day 5Intake and chase compressed into two days; 34 chase calls and texts.
  • Day 8Corrections still trickling in. The pay run executes from the spreadsheet with six packets unverified — trued up a cycle later.
  • Day 10The last packet arrives.
  • Day 12The official PDFs rebuilt in one long sitting.
  • Day 16Filing complete. Hands-on work across sixteen days: about 26 hours. Waiting: everything else.

The four weeks, measured

Office hands-on time, deadline performance, and elapsed days per cycle. Full per-step grid in the appendix.

WeekOffice hands-onIn by the deadlineReturned for correctionWeek ends → all filedNote
W123 h 00 m53 of 70 · 76%137 daysclean run
W224 h 15 m52 of 70 · 74%158 daystypical
W326 h 05 m49 of 70 · 70%179 daysmid-year plan updates hit the review
W424 h 10 m52 of 70 · 74%158 daystypical
Median24 h 15 m74%158 days

Elapsed = the Sunday the week ends to the last packet reviewed, official, and filed. The 16-day December week above sits outside this measured stretch and is reported separately — medians are used throughout so it cannot distort the baseline.